Project name: 4×300MW direct air-cooled heating unit of Ordos Beijiao Thermal Power Co., Ltd. of Mengtai Group
Project location: Ordos City, Inner Mongolia Autonomous Region
Storage capacity: The planned capacity of the power plant is 4×330MW direct air-cooled heating unit project
Running time: 2014

More

Project name: 4×300MW direct air-cooled heating unit of Ordos Beijiao Thermal Power Co., Ltd. of Mengtai Group

Project location: Ordos City, Inner Mongolia Autonomous Region

Storage capacity: The planned capacity of the power plant is 4×330MW direct air-cooled heating unit project

Running time: 2014

 

  • Hydrogen generation: 10Nm3/h
  • Oxygen output: 5Nm3/h
  • Hydrogen purity: 99.8%
  • Oxygen purity: 99.5%
  • Working pressure of electrolyzer: 3.2MPa
  • Unit power consumption: ≤4.8kW.h/ N.m3